- January
2007: The arch is complete!
- 5-19
August 2006: WRG spend a fortnight on site, erecting the bridge
formers and bricklaying.
- 20 November
2005: WRG carry out more clearance work. Plans are being drawn up
for rebuild, which probably have to be from the foundations up.
- May 2003: Excavation is complete.
Plans from 1947 are obtained.
- 15 March
2003: The bottom is reached.
- 1 March
2003: The Kangol effect.
- 15 February
2003: Pipe removed.
- 25 January
2003: The wall comes down.
- 11 January
2003: Uprooting the last of the trees.
- 18 November
2002: A brief return to bridleway construction.
- 14 September: North side of arch
excavated down to towpath level. New pump ("Bernard")
deployed for the first time. Update mid-October.
- 3 August
2002: More storage is moved to site.
- 27 July
2002: The tree stump is removed and the bridleway closed.
- 25 May
2002: Excavation continues with the southwest corner and training
walls.
- 11 May
2002: Excavation begins! A great day.
- 4 May 2002:
The bridleway diversion is inspected and opened.
- 13 April
2002: The bridleway diversion really is completed!
- 2 March
2002: The bridleway diversion is completed.
- 16 February
2002: The Big Blue Box is relocated ready for scalping-spreading
to start.
- 12 January
2002: More work on the temporary bridleway diversion.
- 15 December
2001: Movement of equipment to site.
- 24 November
2001: Completion of works intended for 17 November which were
suspended due to equipment failure.
- 17 November
2001: Work recommences. Movement of scalpings to site for diverted
bridleway.
- Foot-and-Mouth Diseases outbreak
prevents further work until the Winter.
- 17 February
2001: Preparations begin.
|