|
The webmaster was
away sampling oysters in Whitstable, so Orph Mable has kindly supplied
these words and pictures.
It was a mild dry day
with odd moments of sunshine. The slightly depleted team of Chris Forward,
Graham Banks, Phil Large and Orph Mable were on site soon after 9 a.m. Our
Chairman Alan Norris joined us a little after 10 a.m. with some excuse
about a “Bowls Club” do!

The start of the day
The first job was to
pump out the site. Bernard was up and running quickly but seemed to be a
bit sluggish (No - it wasn’t with Alan the previous night!). Phil
quickly dismantled the pump and found it somewhat full of stones and wood
chips. Once re-assembled, Bernard functioned well and quickly reduced the
water level in the working area. Orph was tasked with setting up the small
1" Honda pump on the west side of the workings to carry on when
Bernard dropped the water level below the infill. Recently repaired by
Chris, the little Honda worked well and achieved a very low level of
“sludge” in the western pool in about 2 hours.

The pumps in action
Graham, meanwhile, set
on to get a bonfire alight to clear some of the various stumps and
branches from earlier work-parties. Once the fire was “going”, Graham
and Alan shifted a lot of combustible stuff and improved the tidiness of
the work site. This activity took most of the day.

Graham's fire and Alan's exertions
Once the water level
was below the working area, Phil and Chris set on with the mini-digger to
clear the brick infill and remove the pipe. The method was for Chris to
remove the rubble, placing it behind the digger, then Phil would smash a
3ft pipe section using a sledge hammer. Chris would then remove the
smashed pipe. In this way the pipe and infill was slowly removed. It was
amazing, the amount of rubble that had to be cleared. During this work,
Chris and Phil found some more coping stones which were salvaged for
re-use.

The coping stones and infill after removal of the pipe
By the end of the day,
all the pipe was removed, leaving just the eastern concrete end wall in
place. The invert was cleared down to a concrete layer (approximately 8ins
thick), and the towpath was cleared for 2/3 the width of the bridge. On
the non-towpath side of the bridge we discovered a ledge of bricks
approximately level with the towpath. This was probably used to support
the arch former when the bridge was originally constructed. Additionally,
we discovered a vertical channel in the brick-work at the western edge of
the non-towpath side of the arch, which may have been for stop-planks.
There was even some remains of wood in the groove!

The stop plank - at the left of the base of the brickwork
Considering
the size of the team, much was achieved and all went home, tired but
satisfied that they had met all the targets for the day.
|