West Vale Branch
Projects
Steppingstone Lane Bridge Restoration

12 January 2002
More bridleway diversion work
In December we had moved equipment to site having cleared the route of the bridleway diversion in November. Now that the digger was on-site we could remove the stumps from the copse and profile the ground to reduce gradients. While Phil cracked on with this, Orph and Richard started moving timbers from Alan's garden to site.

Because the diversion is temporary, we want to reclaim the scalpings at the end of its life. To do this we are putting down a liner to put the scalpings on and then placing thick timbers along down each side to retain the scalpings. The timbers chosen appear to be structural beams and are approximately 8"x4" and 6' to 7' long. They were wet and VERY heavy and needed to be carried the quarter mile to site by Richard and Orph on their shoulders. It was absolutely exhausting: the quarter mile walk back just about giving us time to recover for the next one. They did make a very comfortable bench though, as you can see below.

timbers.JPG (80701 bytes)

Whilst Orph and Richard shifted timbers, Phil continued to finish the diversion through the copse - profiling the ground and removing the stumps.

rab_bridleway020112.JPG (273648 bytes)  copsenorth.JPG (83169 bytes)
The re-profiled slope from outside and inside the copse

One particular stump was more troublesome than the others - Phil must have spent the best part of hour removing it.

philstumppulling1_ 12_01_02.JPG (242600 bytes)  philstumppulling2_ 12_01_02.JPG (248146 bytes)
Eventually the stump succumbed
philstumppulling3_ 12_01_02.JPG (83394 bytes)

One reason for his difficulties was a large rock that was caught in its roots. At first we got thought it might have been something to do with the canal, but our hopes proved unfounded.

rock.JPG (81472 bytes) The problematic rock

Orph surveys Phil's handiworkcopsesouth.JPG (81080 bytes)

STEPPINGSTONE LANE BRIDGE RESTORATION INDEX
HOME
    BACK    NEXT

You are visitor