West Vale Branch
Dragonfly Branch Report
Winter 2001/2002

The back-end of 2001 has seen us starting to make progress again after the earlier work stoppages brought about by Foot & Mouth and the summer holiday season. We have managed to catch up on the grass cutting and hedge trimming that had accumulated during the first half of the year and I must admit that the park and towpaths look well cared for at the moment.

Our next major restoration work on the canal is to be Steppingstone Lane Bridge. Readers may remember that we obtained Planning Permission in March 2000 for this work but up to now events have conspired to prevent much being undertaken. Before work can start on the actual bridge, we must re-route the bridleway as this is a heavily used thoroughfare for the local horse riding community. Last year we built a dam either side of the bridge and intend to use the one to the west as a causeway.

In order to prevent damage to the bridleway, we had negotiated with the local farmer to deliver 20 tons of scalpings across his field direct from Station Road. However, we had difficulty in letting a contract for the delivery and the field was ploughed in before the scalpings could be delivered. Thus they were delivered to the canalside car park to await us delivering them to the bridge site.

It was proposed that we had two work parties in November so that we could get the scalpings to site and cut through the small copse to link the diversion with the extant bridleway. The first weekend we hired a 3 ton dumper, large enough to reduce the number of trips down the bridleway to the absolute minimum. Unfortunately, we only achieved 4 deliveries as the hydraulics failed and the dumper refused to turn right! The following weekend, dumper repaired, we tried again.

We started early to ensure that we completed the task in daylight but the best plans never run true! When we started our Kubota mini-digger that was to be used to load the dumper, it was found that the a connecting rod between the lever and the blade control valve had sheared and the blade was stuck in the down position! Whilst 3 stalwarts loaded the dumper in true navvy style (using shovels!), Orph Mable was able to jury rig the digger to enable the blade to be lifted. By mid-morning we were fully mechanised again and Phil Large was able to use the both the digger and dumper to move the scalpings single handed. This freed of the rest of the work party to move down to the bridge and start clearing the diversion route.

By mid-afternoon there was only about 1 ton of scalpings left on the car park, when again the dumper started to refuse to turn right so couldn’t be used for this last load. Undaunted, Phil Large and Orph Mable used our little towpath tractor (converted lawnmower!) and trailer to clear the car park of scalpings by moving them to our storage area. So by the end of the day the scalpings were on-site, and the diversion cut through ready for a few stumps to be pulled next time. The December and January work parties should see the completion of the diversion.

On the social front, November saw the Annual Skittle Challenge taking place between the Abingdon, East Vale and West Vale branches. I am pleased to report that again West Vale were the victors and retained the “beautiful” boat trophy. East Vale came a close second with Abingdon supporting from the rear. Abingdon member George Eycott maintained his record as the lowest scoring gent for the third year running! It was a well supported event and a good time was enjoyed by all.

Members of West Vale Branch hope that 2002 is going to be the year when we get even more canal back in water and we make good progress at Steppingstone Lane Bridge. I am confident that is what I’ll be reporting this time next year.

Orph Mable - Branch Project Co-ordinator

HOME    ARTICLES    BACK

You are visitor