West Vale Branch
Dragonfly Branch Report
Spring 2001

It seems as though 2001 is starting much as 2000 finished, wet and wild. Not weather to be working outside generally but the hardy bunch from West Vale have been busy and progress, I am pleased to report, is again being made on our section. We have been very busy in areas as diverse as the World Wide Web of the Internet to the deep dark dirt of Steppingstone Lane.

The first working party of 2001 was very productive and the good news is that the Cemetery Path is now fully surfaced, looking very good and being regularly used by the good people of Shrivenham, both as part of the Shrivenham Circular Walk and as a safe dog walking route to the canal and Canalside Park. We are still uncertain as whether to install a new “kissing gate” at the park boundary to match the one at the cemetery end. This is a relatively small task and no doubt a decision will be reached in due course. [20/03/01: The kissing gate has now been installed. Click here for details. RB]  

Our February work party was to be used to set up the Steppingstone Lane Bridge (SLB) “base camp” so that work could begin to clear the path for the bridleway diversion before birds start nesting. Plans were made to move the steel container known locally as the “Bluebox” from the car park at the Canalside Park to SLB to give us a dry secure facility for keeping hand tools such as spades and axes and somewhere to store cement, bricks and the like. Additionally we intended to relocate one of our PortaKabin units (kindly donated by a mobile phone company – thanks George) to give us a dry “brew-up” area. Our latest member, Andrew Webb, was able to borrow a very large tractor and trailer to assist in the move and a local building supplier made available a truck with a HIAB crane to assist with the lifting at the park. All was set and fingers were crossed for a good dry period on, and leading up to, the 17th February. 

The approach to SLB site is via a bridle-path which is very soft in parts, so we intended to minimise the number of trips to 3, to avoid cutting it up too much. The plan was that we would send the mini-digger on the trailer first, followed by the Bluebox and then the PortaKabin. All went well, at first, with the day starting foggy but dry. The digger was successfully loaded onto the trailer and despatched with Andrew and the WPO Chris Forward, to SLB whilst the rest of the team readied the Bluebox for the next trip. The Bluebox was raised to approximately 3 ft by the HIAB and was blocked ready to be sat on the trailer. All was set, ready for the tractor and trailer’s return. Which it did, but unfortunately it still had the digger on it!

On reaching SLB, the digger had failed to start so could not be offloaded, leaving Chris & Andrew no option but to return to the Park. After several failed attempts to start the digger, it was eventually off loaded from the trailer (no mean trick without a working engine) and replaced by the Bluebox. Andrew plus 4 trusty stalwarts then travelled with the tractor to SLB to off-load. It was now mid-day! The day had brightened and the ground softened considerably by the time the container arrived at SLB. It was impossible to manoeuvre the trailer into the correct position due to the very soft field edge, and sadly, several very large ruts were made in the field. Plan B eventually came into effect and after contacting the farmer, the Bluebox was deposited in an adjacent grass field.

Back at the Canalside Park, Chris had stripped the digger engine down and found that there appeared to be a problem with the injector pump which would take several days to fix. It was now time to consolidate. The muddy situation at SLB excluded any further move of the PortaKabin so that was shelved until the summer and, hopefully, drier times. The dead digger now needed putting away into the secure shed at the park. Not an easy task but thankfully, by the clever use of a hurriedly manufactured “sledge”, a long electrical umbilical cord, 4x4 Nissan and the large tractor, was achieved without any further mishaps.

It was agreed by all attending that this work party had been very “interesting” if not very successful. “The best laid plans of mice and men………..” Still, it all helps to prevent complacency!

Over the next few months we expect to begin the “archaeological” dig at SLB and hopefully be able to confirm the state of the footings as suitable for restoration. All visitors are asked not to take any vehicles up the bridleway to this site, but to park in Bourton village and walk. This will prevent any conflict with the local residents. [20/03/01: Foot-and-mouth disease has called a halt to further work on Steppingstone Lane Bridge for the time being. RB]

At the beginning of this report, I referred to the WWW. I am now pleased to announce the arrival of the West Vale Branch Web Page! Richard Breese, our branch member from Lambourn and now crowned the West Vale Branch Webmaster, has put together a very informative web site that includes maps and pictures of our section and restoration exploits. In fact there are already several pictures and details of our last work party for all to see. Our web site can be found at http://www.westvalecanal.fsnet.co.uk or follow the links from the Wilts & Berks Canal Amenity Group web site.

The Branch has also been active on the local landowner front during January and February with two very productive meetings with landowners culminating in one letter giving permission to restore the canal across their land with the possibility of a further letter to follow. Additionally, a lease for the land at SLB is nearing completion so much so that we obtained permission for the siting of the SLB “base camp” from the landowner and tenant farmer before the final signatures to the lease which is expected soon.

Hopefully, there will be lots to report in the summer so watch this space (and our web-site) for more exploits of the West Vale Branch.

Orph Mable

HOME    ARTICLES    BACK

You are visitor